US Administration Approves Conditional ~$1 Billion Loan for Three Mile Island Nuclear Plant Restart

US Administration Approves Conditional ~$1 Billion Loan for Three Mile Island Nuclear Plant Restart

The U.S. Department of Energy's Loan Programs Office (LPO) has offered a conditional loan commitment of approximately $1 billion to Constellation Energy. This funding is aimed at facilitating the potential restart of the 819-megawatt Unit 1 reactor at the Three Mile Island (TMI) nuclear power plant in Pennsylvania. The reactor was previously shut down in 2019 due to economic unviability against lower-cost natural gas.

STÆR | ANALYTICS

Context & What Changed

The decision by the U.S. Department of Energy (DOE) to offer a conditional loan commitment for the restart of Three Mile Island (TMI) Unit 1 is a landmark event in U.S. energy policy. TMI is arguably the most infamous nuclear site in the United States due to the partial meltdown of its Unit 2 reactor in 1979. That accident fundamentally altered public perception and halted the growth of the U.S. nuclear industry for decades (source: nrc.gov). TMI Unit 1, a separate and undamaged reactor, operated safely for 45 years until its premature closure in September 2019. The shutdown was not due to safety or operational issues but purely economic factors. The proliferation of low-cost natural gas from the adjacent Marcellus Shale formation suppressed wholesale electricity prices in the PJM Interconnection market, making the plant unprofitable. Unlike nuclear plants in states like Illinois and New York, TMI-1 did not receive state-level subsidies or zero-emission credits that would have leveled the playing field against subsidized renewables and fossil fuels (source: Constellation Energy). The plant was placed in a state of 'safe storage' (SAFSTOR), with its fuel removed and systems mothballed, awaiting eventual decommissioning.

What has changed is the federal policy landscape. The current administration has prioritized decarbonization, grid reliability, and energy security, creating a new strategic imperative for preserving the existing nuclear fleet. Two key pieces of legislation, the Bipartisan Infrastructure Law (BIL) and the Inflation Reduction Act (IRA), have provided powerful new tools to support this goal. The BIL established a $6 billion Civil Nuclear Credit (CNC) program to prevent the premature retirement of economically distressed reactors (source: energy.gov). More significantly, the IRA created a production tax credit (PTC) for existing nuclear plants, offering up to $15 per megawatt-hour for electricity produced, which fundamentally alters the revenue equation for these facilities. Concurrently, the DOE's Loan Programs Office (LPO), armed with hundreds of billions in new loan authority, has been re-energized to finance critical energy infrastructure projects. The conditional loan offer to Constellation is a direct application of these new policy tools, signaling a decisive federal intervention to reverse a market-driven closure and reclaim a major source of zero-carbon baseload power.

Stakeholders

Constellation Energy: As the owner and a leading U.S. nuclear operator, Constellation is the primary actor. The loan de-risks the significant capital investment required for a restart. Success would validate their strategy of positioning nuclear as a critical asset for the clean energy transition and create a valuable, long-term revenue-generating asset.

U.S. Department of Energy (DOE) / Loan Programs Office (LPO): The key government enabler. This project serves the LPO's mandate to finance first-of-a-kind or re-emerging energy technologies and supports the administration's climate and grid reliability goals. A successful restart would be a major policy victory.

Nuclear Regulatory Commission (NRC): The independent federal regulator is a critical gatekeeper. Constellation must submit a comprehensive license amendment request and demonstrate that the plant can be safely restarted and operated after years of dormancy. The NRC's review will be technically rigorous and subject to intense public scrutiny.

PJM Interconnection: The regional grid operator for 13 states, including Pennsylvania. PJM has publicly warned of shrinking reserve margins and future reliability risks as thermal power plants retire faster than new dispatchable resources come online (source: pjm.com). The return of 819 MW of 24/7 power would be a significant boon to grid stability.

Pennsylvania State Government: The state's previous inaction on subsidies was a key factor in the 2019 closure. The federal intervention may prompt Harrisburg to reconsider policies, such as including nuclear in its Alternative Energy Portfolio Standard, to provide further long-term stability.

Local Community (Dauphin County, PA): Interests are divided. A restart promises hundreds of high-paying, long-term jobs and a substantial increase in the local tax base. However, the legacy of the 1979 accident means safety concerns remain a potent political and social issue.

Competitor Generators (Natural Gas, Coal): The restart of TMI-1 would directly displace generation from fossil fuel plants in the PJM market, reducing their operating hours and revenues. This represents a direct threat to the economics of regional gas and coal fleets.

Environmental & Anti-Nuclear Organizations: These groups are expected to mount significant opposition, citing safety risks, the unresolved issue of long-term nuclear waste storage, and the plant's age. They will likely use regulatory comment periods and litigation to challenge the restart.

Evidence & Data

Plant Specifications: TMI Unit 1 is an 819-megawatt (MW) pressurized water reactor that entered service in 1974 (source: Constellation). Its closure removed approximately 6.5 Terawatt-hours (TWh) of carbon-free electricity from the grid annually, assuming a typical >90% capacity factor.

Financial Incentive: The IRA's nuclear PTC provides a tax credit of up to 0.3 cents/kWh ($3/MWh), which can increase fivefold to 1.5 cents/kWh ($15/MWh) if wage and apprenticeship requirements are met. For a plant like TMI-1, this could represent over $90 million in additional revenue or tax benefit per year (calculation: 819 MW
0.9
8760 hrs
$15/MWh).

Loan Precedent: This is not the first such action. In March 2024, the LPO finalized a $1.52 billion loan to Holtec International to restart the 800 MW Palisades nuclear plant in Michigan, which had closed in 2022 (source: energy.gov). This established a clear precedent and a procedural roadmap for the TMI-1 project.

Grid Reliability Data: PJM's 2023 Regional Transmission Expansion Plan report noted concerns about resource adequacy, highlighting the accelerated retirement of thermal generation as a key risk to maintaining reliability (source: pjm.com). The 819 MW from TMI-1 represents a significant portion of dispatchable capacity.

Carbon Abatement: The annual generation of ~6.5 TWh from TMI-1 would displace an equivalent amount of generation, primarily from natural gas combined-cycle plants in the PJM market. This would avoid approximately 2.6 million metric tons of carbon dioxide emissions annually (author's calculation based on EIA emissions factors for natural gas).

Scenarios (3) with probabilities

Scenario 1: Successful Restart (Probability: 60%)

Constellation formally accepts the loan, successfully navigates the NRC relicensing process, and completes the necessary refurbishment on schedule and within a manageable budget. The plant returns to service by 2028-2029. Supported by the federal PTC and PJM capacity market revenues, it operates as a profitable, long-term source of zero-carbon power. This scenario is supported by strong federal backing, a clear technical precedent at Palisades, and the urgent grid reliability needs identified by PJM. The primary challenges are execution-focused: managing the complex technical and regulatory pathways.

Scenario 2: Delayed and Over-Budget Restart (Probability: 30%)

The project moves forward but encounters significant hurdles. The NRC review process becomes protracted due to legal challenges or the discovery of novel technical issues. Refurbishment is plagued by supply chain delays for specialized components and cost overruns, pushing the final project cost significantly above the initial ~$1.2-1.5 billion estimate. The plant eventually restarts but its financial viability is compromised by the higher debt load and delayed revenue generation. This scenario is plausible given the inherent complexity of restarting a 50-year-old industrial facility that has been dormant for several years.

Scenario 3: Project Abandonment (Probability: 10%)

Despite the initial momentum, the project is ultimately cancelled. This could be triggered by a ‘fatal flaw’ discovery during detailed inspections—for example, irreparable degradation of the reactor pressure vessel. Alternatively, a sharp and sustained collapse in energy market prices combined with a future change in federal administration that repeals the IRA’s PTC could destroy the project’s economic foundation. While unlikely given the current policy environment and sunk costs, the conditional nature of the loan provides an off-ramp if insurmountable obstacles emerge.

Timelines

Near-term (0-12 Months): Constellation makes a Final Investment Decision (FID) and formally accepts the loan terms. The company initiates detailed engineering assessments and submits its formal License Amendment Request (LAR) to the NRC to authorize a restart.

Mid-term (1-3 Years): The NRC conducts its technical and safety reviews of the LAR, a process likely to take at least 24 months and involve public comment periods. In parallel, Constellation begins on-site refurbishment work, procures long-lead-time components like turbine blades and control systems, and ramps up hiring and training.

Long-term (3-5 Years): Assuming NRC approval, Constellation completes refurbishment and system-wide testing. The company would then load new nuclear fuel, conduct criticality and power ascension testing, and synchronize the plant to the grid. A realistic target for return to commercial operation would be in the 2028-2030 timeframe (author's assumption based on the Palisades project timeline).

Quantified Ranges

Total Project Cost: The ~$1 billion loan suggests a total project cost in the range of $1.2 billion to $1.7 billion, with the federal loan covering a substantial portion of the capital required. This is comparable to the estimated costs for the Palisades restart (source: Holtec).

Annual Economic Output: At recent PJM wholesale energy and capacity prices, plus the IRA PTC, the plant's annual revenue could be in the range of $300 million to $500 million.

Direct Employment: The restart would create 1,000-1,500 temporary construction and refurbishment jobs over several years, followed by 500-700 permanent, high-paying operational jobs, consistent with plants of similar size (source: Nuclear Energy Institute).

Risks & Mitigations

Regulatory Risk: The NRC's approval process is the project's most significant external hurdle. Delays or denial are possible.

Mitigation: Constellation must engage in a transparent, technically exhaustive process with the NRC, leveraging its extensive operational experience and the lessons learned from the ongoing Palisades restart application. A proactive community and stakeholder engagement plan is essential.

Technical & Execution Risk: Restarting a long-dormant plant carries inherent risks of discovering unexpected component degradation or facing complex refurbishment challenges.

Mitigation: The project should be structured in gated phases, with continued investment contingent on passing key technical milestones. The conditional loan allows for off-ramps if pre-FID inspections reveal insurmountable problems.

Market Risk: While the IRA provides a 10-year buffer, the plant's long-term viability depends on post-IRA market conditions. A sustained depression in electricity prices could threaten profitability in the 2030s.

Mitigation: Constellation can hedge against this risk by securing long-term Power Purchase Agreements (PPAs) with large, creditworthy offtakers such as data centers, technology companies, and industrial users seeking guaranteed 24/7 clean power.

Political & Public Opposition Risk: Given TMI's history, public opposition could fuel legal and political challenges.

Mitigation: A sophisticated communications strategy is required, focusing on the plant's safety record, economic benefits (jobs, taxes), and its critical role in ensuring regional grid reliability and achieving climate goals.

Sector/Region Impacts

U.S. Nuclear Sector: This is a transformative development. It solidifies a federal policy framework that redefines existing nuclear plants as critical infrastructure assets worthy of preservation. It creates a viable template for other operators to consider restarting prematurely shuttered plants (e.g., Kewaunee in Wisconsin) or reversing closure decisions for currently operating but at-risk reactors.

PJM Grid & Mid-Atlantic Region: The impact is overwhelmingly positive for grid reliability. The addition of 819 MW of firm, weather-independent capacity provides a crucial backstop against the intermittency of renewables and the retirement of thermal plants, reducing the risk of capacity shortfalls and price volatility.

Natural Gas Sector: The impact is negative. TMI-1 will run at a very high capacity factor, displacing thousands of hours of generation from natural gas plants, thereby reducing their revenues and the regional demand for natural gas.

Investment & Finance: The use of the LPO to backstop a restart fundamentally de-risks the project for private capital. It signals to markets that the federal government is willing to act as a cornerstone investor to achieve strategic energy policy goals, potentially unlocking further private investment in the nuclear sector.

Recommendations & Outlook

For Infrastructure Investors & Operators: The TMI-1 and Palisades projects establish a new asset class: the government-backed restart of nuclear facilities. This model should be evaluated for other prematurely closed plants where technical viability remains. The key is to secure federal backing before committing significant private capital.

For Policymakers: (Scenario-based assumption: The primary policy goals remain decarbonization and grid security). The federal government should streamline the process for evaluating and supporting such projects. State governments, particularly in PJM and MISO regions, should align their clean energy policies to recognize the reliability and clean air attributes of nuclear power, ensuring long-term market certainty beyond the 10-year IRA window.

For Corporate Energy Buyers: The availability of government-backed, long-term nuclear generation presents a unique opportunity to secure 24/7 carbon-free energy through PPAs. This is particularly valuable for industries with high-load factors like data centers and heavy manufacturing.

Outlook: (Scenario-based assumption: Based on the 'Successful Restart' scenario). The conditional loan for TMI-1 is more than a financial transaction; it is a profound policy statement. It marks the full reversal of a 40-year narrative of nuclear decline in the U.S. and its repositioning as a central pillar of the nation's future energy infrastructure. The success of this project would not only add a critical asset back to the grid but would also create a powerful, replicable model for preserving and enhancing the nation's largest source of carbon-free electricity. The execution of this restart will be a critical bellwether for the future of the entire U.S. nuclear industry and the credibility of the nation's energy transition strategy.

By Amy Rosky · 1763632887