UK energy bill payers will hand £2bn a year to EDF for new power stations

UK energy bill payers will hand £2bn a year to EDF for new power stations

The UK government has finalized a subsidy model where energy bill payers will provide approximately £2 billion annually to the French state-owned company EDF. This funding is designated for the construction and operation of two new nuclear power stations, Hinkley Point C and Sizewell C, representing a major long-term financial commitment to nuclear energy.

STÆR | ANALYTICS

Context & What Changed

The United Kingdom’s energy policy is driven by two primary objectives: achieving statutory net-zero greenhouse gas emissions by 2050 (source: gov.uk) and ensuring national energy security, a goal amplified by the geopolitical volatility affecting natural gas supplies. Within this framework, new nuclear power is positioned as a critical source of reliable, low-carbon baseload electricity to complement intermittent renewable sources like wind and solar. This news item crystallizes the direct financial consequence of this strategy for the public. The £2 billion annual cost to be borne by consumers via levies on their energy bills is not a new policy, but its quantification in the public domain marks a significant moment of clarity regarding the long-term financial burden of constructing Hinkley Point C (HPC) in Somerset and Sizewell C (SZC) in Suffolk.

What has changed is the transition from abstract policy and project estimates to a concrete, recurring annual cost. This figure combines the impact of two different financing models. Hinkley Point C is funded under a Contract for Difference (CfD) model, which guarantees its operator, EDF, a fixed, inflation-adjusted price for electricity (£92.50 per MWh in 2012 prices) for 35 years post-completion (source: National Audit Office). If the market price is lower, consumers pay the difference. Sizewell C, a planned replica of HPC, will be financed under a newer Regulated Asset Base (RAB) model, enabled by the Nuclear Energy (Financing) Act 2022 (source: legislation.gov.uk). The RAB model allows the developer to begin receiving revenue from consumers during the lengthy construction phase, lowering the cost of capital by shifting financing risk from the developer to the public. The £2 billion figure represents the combined effect of these mechanisms, making the cost of the UK's nuclear strategy tangible for every household and business.

Stakeholders

UK Government (Department for Energy Security and Net Zero): The primary architect of the policy, balancing long-term energy security and decarbonization goals against the immediate cost-of-living impact on the public. The government is also a direct 50% equity partner in the Sizewell C project, placing public funds at direct risk (source: gov.uk).

EDF (Électricité de France): The French state-owned energy giant is the developer and future operator of both plants. It is the main recipient of the £2 billion annual funding stream and is responsible for managing the immense construction challenges.

UK Consumers and Businesses: The ultimate funders of the projects. They bear the direct cost through levies on their energy bills, with limited control over project execution or cost overruns, particularly under the RAB model for SZC.

Ofgem (The Office of Gas and Electricity Markets): The UK's energy regulator is tasked with implementing the financing frameworks and protecting consumer interests, a role that involves significant tension in balancing long-term strategic goals with short-term consumer costs.

Infrastructure Investors: The RAB model for SZC is designed to attract private capital by offering a more stable, government-backed return profile. The success of this model is being closely watched by global infrastructure funds.

Supply Chain Companies: A vast ecosystem of engineering, construction, and manufacturing firms in the UK and abroad depend on these multi-decade projects for significant contracts and employment.

Competitor Energy Generators: Developers of renewables, gas power plants, and emerging technologies (like long-duration storage) compete for capital and policy support. This large-scale commitment to nuclear power influences the investment landscape for all other energy sources.

Evidence & Data

The financial commitments are substantial and long-term. The £2 billion annual figure is the headline cost flow (source: theguardian.com). The underlying project costs are immense and have a history of escalation.

Hinkley Point C (HPC): This 3.2 GW plant is already deep into construction. Its initial cost estimate in 2016 was £18 billion. As of early 2024, EDF revised the cost estimate to a range of £31-£34 billion in 2015 prices, which could equate to as much as £46 billion in nominal terms (source: EDF). The operational start date for the first reactor has been delayed from 2025 to 2029 at the earliest, with 2031 being a possibility (source: EDF). The National Audit Office estimated in 2017 that the total lifetime cost to consumers for the CfD top-up payments would be £30 billion; this figure is now certain to be significantly higher due to construction delays and inflation.

Sizewell C (SZC): This project, also 3.2 GW, is intended to be a near-identical copy of HPC to save on design and engineering costs. Its initial cost was estimated at around £20 billion (source: gov.uk). The RAB financing model is projected by the government to save consumers £30 billion over the project's life compared to a CfD model like HPC's, due to lower financing costs (source: gov.uk). However, this saving comes at the price of consumers bearing the risk of financing the project during construction, before it generates any electricity.

Combined Impact: The two plants are expected to generate approximately 7% (HPC) and 6% (SZC) of the UK's electricity, respectively, providing power for roughly 6 million homes each (source: EDF). Together, they represent a significant portion of the UK's future low-carbon, firm power capacity.

Scenarios (3) with probabilities

Scenario 1: Successful, Albeit Delayed, Delivery (Probability: 40%)

Both Hinkley Point C and Sizewell C are completed and become operational, but with further moderate delays (2-3 years beyond current estimates) and cost overruns (15-25% above current budgets). The £2bn annual cost to consumers proves to be a durable average but fluctuates with inflation and wholesale energy prices. The plants provide a critical baseload of low-carbon power, contributing significantly to the UK’s 2050 net-zero target and enhancing energy security. The government deems the high cost a necessary price for these strategic benefits. The RAB model for SZC is considered a qualified success, having attracted private investment and kept financing costs below what they would have been under a CfD.

Scenario 2: Chronic Delays and Severe Cost Escalation (Probability: 50%)

Mirroring the track record of European Pressurised Reactor (EPR) projects globally (e.g., Olkiluoto 3 in Finland, Flamanville in France), both UK projects face further significant delays and budget blowouts exceeding 30% of current estimates. The annual cost to consumers regularly surpasses the £2bn estimate, fueling intense political and public opposition. The government is forced to inject additional direct public funds into Sizewell C to prevent its collapse, increasing national debt. The viability of any future large-scale nuclear projects in the UK is called into question, and the long-term cost-effectiveness of the nuclear strategy is severely undermined.

Scenario 3: Project Curtailment or Cancellation (Probability: 10%)

A confluence of extreme cost escalation at Sizewell C, a major technical setback, or a fundamental shift in government policy following an election leads to the cancellation of the SZC project mid-construction. This results in billions in sunk costs borne by taxpayers and bill payers, a major diplomatic and commercial dispute with EDF and other investors, and a critical gap in the UK’s long-term energy plan. The UK’s reputation for delivering major infrastructure projects is severely damaged, chilling future international investment in the sector.

Timelines

Hinkley Point C: Construction began in 2016. Unit 1 is now forecast to be operational between 2029 and 2031. The 35-year CfD payment period begins upon commissioning.

Sizewell C: A Final Investment Decision (FID) is anticipated in 2024/2025. Construction is estimated to take 9-12 years, placing the earliest operational date in the late 2030s. Payments from consumers under the RAB model will begin during the construction phase, well before the plant generates power.

Annual Levy: The £2bn annual cost will ramp up. Initial costs will be driven by the SZC RAB payments, with the full impact materializing in the early 2030s when HPC is fully operational and its CfD payments begin, while SZC is still under construction and drawing RAB financing.

Quantified Ranges

Annual Consumer Cost: Approximately £2 billion, which translates to a levy of roughly £70 per year per UK household (£2bn / ~28 million households), subject to inflation and final project costs.

Total Capital Cost (HPC & SZC): A combined baseline estimate is in the range of £55-£65 billion in nominal terms, with a high probability of exceeding this range.

Total Lifetime Cost to Consumers: This will run into the tens of billions of pounds for each plant. For HPC alone, the initial £30 billion NAO estimate is now a floor, not a ceiling. The total cost for both plants over their respective subsidy periods will likely exceed £100 billion.

Risks & Mitigations

Risk: Construction & Execution Risk: The primary risk is the failure to control costs and schedules, a historical weakness of large nuclear builds.

Mitigation: Using a 'replica' design for SZC is intended to reduce first-of-a-kind engineering risks. The presence of government as a major equity partner in SZC is meant to provide stronger oversight. However, the fundamental complexity of the projects remains.

Risk: Financial & Funding Risk: For SZC, the risk is failing to attract sufficient private capital alongside the government's stake, even with the de-risking offered by the RAB model.

Mitigation: The RAB model is the core mitigation, designed to provide a secure, regulated return that is attractive to pension and infrastructure funds. Government investment provides an anchor and a signal of confidence.

Risk: Political & Regulatory Risk: A future government could alter or withdraw support, particularly for SZC, creating massive uncertainty.

Mitigation: Binding legal agreements and the cross-party political consensus (to date) on the need for new nuclear provide some protection. The sheer scale of sunk costs also creates a strong disincentive to cancel.

Risk: Market & Technology Risk: The fixed-price support for HPC could appear grossly uneconomical if long-term wholesale electricity prices fall due to cheaper renewables and energy storage breakthroughs.

Mitigation: The government's position is that this is a premium paid for energy security and non-intermittent clean power, a hedge against fossil fuel price volatility. This risk is largely unmitigated for consumers locked into the 35-year CfD.

Sector/Region Impacts

Energy Sector: This decision solidifies the central role of nuclear power in the UK's energy mix for the second half of the 21st century. It may, however, absorb a disproportionate share of investment and policy focus, potentially 'crowding out' other promising technologies like geothermal, tidal, or advanced modular reactors.

Public Finance: While the cost is levied on bills rather than general taxation, it is a government-mandated transfer of wealth on a massive scale. The government's direct equity stake in SZC also creates a significant, long-term liability on the public balance sheet.

Regional Economy: The projects are transformative for their local regions (Somerset and Suffolk), creating thousands of high-skilled jobs during construction and long-term operation, and fostering a specialized industrial supply chain.

UK Industry: The policy represents a major strategic bet on a specific technology and a single primary industrial partner (EDF), raising questions about industrial diversification and sovereign capability in a critical sector.

Recommendations & Outlook

For Government & Regulators: It is imperative to establish an exceptionally rigorous and transparent oversight regime for Sizewell C's construction under the RAB model. Any cost overruns will be directly and immediately passed to consumers, making robust project governance essential to maintain public consent. (Scenario-based assumption: The government proceeds with SZC's FID). A parallel, aggressive strategy to foster competition and innovation in other firm power technologies (e.g., long-duration storage, geothermal, Small Modular Reactors) is critical to avoid excessive technological and financial dependency on the EPR program.

For Industry Actors (EDF & Supply Chain): The single most important task is to demonstrate that the 'learning by doing' from Hinkley Point C can translate into tangible cost and time savings at Sizewell C. Failure to do so will validate critiques of the technology's affordability and could terminate the UK's nuclear renaissance. Proactive management of the supply chain and skilled labor pipeline is crucial.

For Investors: The UK's commitment to the RAB model is a significant de-risking signal. However, investors must conduct deep due diligence on the specific regulatory mechanics, the potential for political interference, and EDF's ability to manage the immense execution risk. (Scenario-based assumption: The government successfully attracts private capital for SZC).

Outlook: The £2 billion annual commitment is the price of the UK's strategic decision to rebuild its nuclear fleet to achieve energy security and decarbonization. This path is now largely set for the coming decades. The policy locks in significant, non-discretionary costs for consumers and creates a path dependency that will shape the UK energy market for generations. The ultimate success of this strategy hinges entirely on execution. If Hinkley Point C and Sizewell C can be delivered without further major escalations, they will be cornerstones of a stable, low-carbon grid. If they repeat the historical pattern of severe delays and cost overruns, they will become a multi-decade case study in the perils of state-directed mega-projects and a lasting financial burden on the UK economy.

By Lila Klopp · 1764334874